Gujarat: Additional Surcharge (state DISCOMs) rises to ₹0.99/kWh, from ₹0.76/kWh
Typical factory:Third-party PPA: +₹6.6 lakh/yrGroup captive: no changeSource: GERC Order No. 05 of 2026 dated 10-Sep-2026 - September 2026
-
Gujarat: Banking charge on banked energy (GEOA) falls to ₹1.00/kWh, from ₹1.50/kWh
Typical factory:Third-party PPA: −₹2.2 lakh/yrGroup captive: −₹2.2 lakh/yrSource: GERC Green Energy Open Access (Sixth Amendment) Regulations, 2026, Reg. 17.6 - April 2026
-
Maharashtra — Tata Power-D (Mumbai): InSTS transmission loss (MERC trajectory) falls to 3.26%, from 3.28%
Typical factory:Third-party PPA: no changeGroup captive: no changeSource: MERC InSTS order, Case No. 208 of 2024 dated 28-Mar-2025 -
Maharashtra — Tata Power-D (Mumbai): InSTS transmission charge — RE medium/long-term OA, per-unit option falls to ₹1.04/kWh, from ₹1.16/kWh
Typical factory:Third-party PPA: −₹3.5 lakh/yrGroup captive: −₹3.5 lakh/yrSource: MERC InSTS order, Case No. 208 of 2024 dated 28-Mar-2025 -
Maharashtra — MSEDCL: InSTS transmission loss (MERC trajectory) falls to 3.26%, from 3.28%
Typical factory:Third-party PPA: no changeGroup captive: no changeSource: MERC InSTS order, Case No. 208 of 2024 dated 28-Mar-2025 -
Maharashtra — MSEDCL: InSTS transmission charge — RE medium/long-term OA, per-unit option falls to ₹1.04/kWh, from ₹1.16/kWh
Typical factory:Third-party PPA: −₹3.5 lakh/yrGroup captive: −₹3.5 lakh/yrSource: MERC InSTS order, Case No. 208 of 2024 dated 28-Mar-2025 -
Gujarat: STU (GETCO) transmission charge — long/medium-term OA falls to ₹3,858.96/MW/day, from ₹3,918.01/MW/day
Typical factory:Third-party PPA: −₹0.4 lakh/yrGroup captive: −₹0.4 lakh/yrSource: GERC GETCO tariff order, Case No. 2419/2024 dated 29-Mar-2025